THE COST ESTIMATE

The Cost Estimate: Intro

AERATION DIFFUSION SYSTEM:

COST ESTIMATE

The Capital Expenditure - $250,000 to $300,000
The Cost per Diffuser - $10,000

The aeration diffusion system chosen for this site has a 5 year warranty for system components, and a 30 year life expectancy.
Initial risk of an algae bloom when system first implemented, however the risk dissipates within the first 4-6 weeks of operation.

The Cost Estimate: Body

OPERATION AND MAINTENANCE

Yearly O&M Cost - $500 to $1000
Energy Demand - $31,000 per year

The Operation and Maintenance for this system involved daily monitoring of the system. This amounts to approximately 30 minutes of monitoring per day of the system. Daily O&M ensures optimum and uniform airflow across all diffusers.

The Cost Estimate: Body

REHABILITATION CHANNEL:

COST ESTIMATE

Excavation Cost - $347,501
Cost per Cubic Yard - $82 per CY
Materials Cost - $298,707
Total Capital Cost - $646,208

Listed above is the Capital Expenditures Cost Estimate for the Rehabilitation Channel. 
The approximate amount of soil that will need to be excavated is 325 cubic yards.

The Cost Estimate: Body

OPERATION AND MAINTENANCE

Cost per Day of Coagulants - $83 per day
Flocculant Removal Cost - $520
Monthly O&M Cost - $3,537 per month

The Operation and Maintenance (O&M) for the rehabilitation channel is bi-weekly. The O&M consists of a bi-weekly removal and disposal of flocculated material.

The Cost Estimate: Body

FOCUSED DREDGING:

COST ESTIMATE

Dredging Cost - $116,782
Cost per Cubic Yard - $3.20
Material Disposal Cost - $918,300
Total Cost - $1,080,969

Initial dredging cost estimate take into account the cost of labor and equipment use. Labor taxes and insurances were taken from historical data and equipment based on availability and our project size.

Approximate soil volume to be dredged and remediated is 36,730 cubic yards. 

Volume of water to be treated estimated at 345 acre-ft. 

​

Note: There is no cost estimate required for the Operations and Maintenance for Focused Dredging, as this is a one-time occurrence.

The Cost Estimate: Body
rec.PNG
The Cost Estimate: Image